Data report · 2026 edition
The State of FAA Obstruction Filings
Every structure tall enough to matter near an American airport gets filed with the FAA, and every one of those filings is public. Almost nobody reads them in aggregate. We parsed 1,815,083 Part 77 notices to answer the questions the industry argues about without evidence: how long the FAA really takes, what is actually being built, and who does the filing.
Free to use and quote under CC BY 4.0: credit LOS Analyzer. Every table below downloads as CSV, and a link back is appreciated. Corrections are genuinely welcome — the queries behind every figure are described in the methodology.
Corrected 2026-10-02: an earlier version counted adverse 'To Proponent' determinations among expiring determinations (published as 113,812); the figure now counts No Hazard determinations only: 74,565 expiring from October 2026 to September 2027, with extended determinations shown separately (a further 14,555 in that window). That version's six-month subtotal also covered seven months, and it overstated the largest representative's lead over the next firm as 'more than triple'. Its count of organisations filing for the first time ran from a fixed start date; it now covers exactly the twelve months to the archive date. This version also moves the data to the September 12, 2026 archive.
Source: FAA Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) public archive (oeaaa.faa.gov), data as of September 12, 2026. Compiled by LOS Analyzer (Idea Engine LLC). This is not an official FAA record or an FAA determination; the FAA's portal is authoritative. LOS Analyzer is not affiliated with or endorsed by the FAA.
Compiled analysis © Idea Engine LLC, licensed CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/) — credit 'LOS Analyzer'. Underlying FAA data is public domain.
The five findings
Filings, 2015 → 2025
2.9×
From 51,758 notices in 2015 to 148,680 in 2025. The obstruction docket has grown faster than almost anyone in the industry describes it.
Median wait, wind vs oil rig
125 vs 24 days
A wind turbine waits 5.2× as long as a drilling rig for the same kind of determination. What you are building predicts your schedule better than where you are building it.
Hazard determinations issued
8
Out of 216,895 determinations since January 2025. The FAA almost never says "hazard" outright — it sends 51,286 cases back to the proponent instead.
No-hazard determinations expiring in 12 months
74,565
Unbuilt projects whose no-hazard determination lapses between October 2026 and September 2027. Each one is a re-filing nobody is being reminded about.
Share of outsourced filings held by 10 firms
32.7%
Of 121,404 filings made by a representative on someone else's behalf, ten firms carry a third — out of 5,076 that file at all.
Organisations that filed for the first time
2,890
First-ever FAA obstruction filing in the twelve months from September 12, 2025 to September 11, 2026. The market has a large, constantly renewed population of people doing this for the first time.
1. The docket has nearly tripled in a decade
In 2015 the FAA received 51,758 off-airport Part 77 notices. In 2025 it received 148,680. That is 2.9 times the volume, absorbed by an agency whose obstruction evaluation staffing has not grown at anything like the same rate.
The step changes are worth noting. Volume jumps in 2021 and again in 2024, which tracks the build-out of wireless infrastructure and the return of utility-scale renewables. Nothing in this series suggests the trend is levelling off.
Off-airport Part 77 filings per year, 2015–2026
2026 is a partial year, shown in grey — the archive runs through September 12, 2026.
View as table
| Year | Filings |
|---|---|
| 2015 | 51,758 |
| 2016 | 67,888 |
| 2017 | 69,320 |
| 2018 | 88,512 |
| 2019 | 91,246 |
| 2020 | 92,494 |
| 2021 | 121,135 |
| 2022 | 133,054 |
| 2023 | 127,916 |
| 2024 | 140,169 |
| 2025 | 148,680 |
| 2026 | 117,253 |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
2. What you are building decides how long you wait
This is the finding we expected to be smaller than it is. Across 212,098 determined cases since January 2025, the average case closes in 62.9 days. But the average hides a spread that matters enormously if you are the one waiting.
A wind turbine takes a median of 125 days to a determination. A rig takes 24. Cranes, which are the most schedule-sensitive filings anyone makes, sit near the fast end.
If you are planning a wind project, the practical consequence is that airspace review is a two-to-four month line item, not a formality you handle during permitting. Treating it like a crane filing is how schedules slip.
Median days from filing to determination, by structure type
Determined cases since January 2025, structure types with at least 500 determinations. Median rather than mean, so a handful of multi-year outliers cannot carry the ranking.
View as table
| Structure type | Median days |
|---|---|
| Wind turbine | 125 days |
| Road rail | 68 days |
| Terrain vegetation | 66 days |
| Airport development | 66 days |
| Other | 64 days |
| Fence | 62 days |
| Construction equipment | 58 days |
| Sign | 54 days |
| Antenna tower | 43 days |
| Power line | 37 days |
| Building | 37 days |
| Tank stack | 37 days |
| Crane | 32 days |
| Pole lighting | 31 days |
| Solar | 28 days |
| Rig | 24 days |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
3. Wind collapsed, then came back four times over
Wind turbine notices peaked at 11,506 in 2018, fell to 5,018 by 2021, and reached 21,164 in 2025. That is a 4.2× recovery from the trough, and it makes wind the single most volatile category in the entire obstruction docket.
Read alongside the previous chart, this is the squeeze the wind industry is currently in. It is filing at record volume in the category the FAA takes longest to clear.
Wind turbine Part 77 filings per year, 2015–2026
The 2021 trough is marked. 2026 is a partial year.
View as table
| Year | Wind turbine filings |
|---|---|
| 2015 | 4,598 |
| 2016 | 4,950 |
| 2017 | 6,134 |
| 2018 | 11,506 |
| 2019 | 8,216 |
| 2020 | 5,914 |
| 2021 | 5,018 |
| 2022 | 7,357 |
| 2023 | 13,506 |
| 2024 | 19,083 |
| 2025 | 21,164 |
| 2026 | 12,118 |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
4. Most filings are not buildings
The mental image of obstruction evaluation is a tall building near a runway. The data says otherwise. Power lines, cranes and construction equipment together account for far more filings than buildings do, and buildings rank seventh.
This matters for anyone selling into the space, or staffing for it. The typical 7460 filer is a utility, a crane dispatcher or a tower contractor, not an architect.
Filings by structure type, January 2025 onward
Top ten categories. The pipeline's structure classifier groups the FAA's free-text structure types into these families.
View as table
| Structure type | Filings |
|---|---|
| Power line | 57,690 |
| Crane | 41,220 |
| Construction equipment | 39,073 |
| Wind turbine | 33,282 |
| Antenna tower | 32,548 |
| Pole lighting | 16,542 |
| Building | 15,165 |
| Rig | 10,360 |
| Other | 6,665 |
| Solar | 2,992 |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
5. The FAA almost never says “hazard”
Since January 2025 the FAA has issued 216,895 determinations on off-airport Part 77 cases. 8 of them were a determination of hazard. Not 8 percent of them. 8 cases in total.
This is the single most misunderstood thing about the process. People plan around the fear of a hazard determination, and that is not the outcome that actually stops projects. The outcome that stops projects is “To Proponent”: 51,286 cases, 23.6% of all determinations, where the FAA hands the case back with something the filer has to resolve. Meanwhile 71.8% come back clean.
The practical reading: the risk in a 7460 filing is rarely a flat refusal. It is delay, conditions, and rework — which is exactly the risk a screening before you file is meant to retire.
No hazard
71.8%
155,719 determinations
Back to proponent
23.6%
51,286 determinations
Hazard
8
determinations, in 20 months
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
6. A third of outsourced filing runs through ten firms
121,404 filings since January 2025 were submitted by a representative acting for someone else. 5,076 distinct organisations do that work, but the top ten carry 32.7% of it.
Capitol Airspace Group alone filed 14,411 cases for 489 different clients — 2.8 times as many as the next firm. Several names on this list are not consultancies at all but tower owners and utilities filing for their own affiliates, which is worth remembering before reading the table as a market-share ranking.
| Representative | Filings | Clients |
|---|---|---|
| Capitol Airspace Group | 14,411 | 489 |
| American Tower Corporation | 5,134 | 26 |
| Crown Castle | 3,662 | 21 |
| Burns & McDonnell | 3,015 | 118 |
| Network Regulatory - C | 2,827 | 27 |
| Oncor Electric Delivery | 2,714 | 15 |
| POWER Engineers | 2,336 | 18 |
| Westslope Consulting, LLC | 2,190 | 18 |
| Network Regulatory | 1,689 | 25 |
| Vertical Bridge REIT, LLC | 1,662 | 25 |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Organisations only; individual filers are excluded. Download CSV
7. Where the filings are
Texas files more Part 77 notices than any other state by a wide margin, driven by wind, oil and gas rigs, and transmission. Florida is second, on a very different mix of power lines and cranes.
By airport, CHICAGO O'HARE INTL is in a category of its own with 5,442 filings naming it as the nearest airport, more than three times MIAMI INTL. Note this counts the nearest airport recorded on the notice, so a dense metro with one dominant field will concentrate here.
Top states
| TX | 35,494 |
| FL | 24,761 |
| CA | 17,474 |
| IL | 13,903 |
| VA | 8,294 |
| NV | 8,046 |
| MN | 7,990 |
| MO | 6,971 |
| MI | 6,914 |
| OH | 6,821 |
Top airports by nearby filings
| CHICAGO O'HARE INTLIL | 5,442 |
| MIAMI INTLFL | 1,727 |
| TAMPA INTLFL | 1,516 |
| PENSACOLA INTLFL | 1,493 |
| WASHINGTON DULLES INTLVA | 1,442 |
| AVENGER FLDTX | 1,401 |
| GEORGE BUSH INTCNTL/HOUSTONTX | 1,372 |
| ST LOUIS LAMBERT INTLMO | 1,125 |
| LOUIS ARMSTRONG NEW ORLEANS INTLLA | 1,120 |
| ORLANDO INTLFL | 1,063 |
8. 74,565 no-hazard determinations expire in the next year
A further 14,555 extended determinations also expire in this window: no-hazard determinations the FAA has already extended, counted separately.
A no-hazard determination is not permanent. If the structure is not built, the determination lapses and the project has to go back through the process. Counting only No Hazard determinations on organisation-sponsored cases with no recorded build date, 74,565 expire in the twelve months from October 2026 to September 2027, 37,503 of them by the end of March 2027. “To Proponent” cases also carry an expiration date in the archive, but they are not a determination of no hazard, so they are not counted (correction).
The peak is June 2027, with 8,487 expiring across 720 organisations. Nobody sends these reminders. The expiration date sits in a public record that almost no filer is watching.
No-hazard determinations expiring, October 2026 – September 2027
No Hazard determinations on organisation-sponsored cases with no recorded build date, by month of expiry: the twelve full months after the archive date. The peak month is highlighted.
View as table
| Month | Expiring |
|---|---|
| Oct 26 | 8,149 |
| Nov 26 | 5,155 |
| Dec 26 | 4,099 |
| Jan 27 | 7,362 |
| Feb 27 | 6,521 |
| Mar 27 | 6,217 |
| Apr 27 | 3,611 |
| May 27 | 2,785 |
| Jun 27 | 8,487 |
| Jul 27 | 8,216 |
| Aug 27 | 6,197 |
| Sep 27 | 7,766 |
Source: FAA OE/AAA public archive, data as of September 12, 2026. Download CSV
Methodology, and what these numbers do not say
Source. The FAA's Obstruction Evaluation / Airport Airspace Analysis public archive, downloaded per region and year as the agency publishes it. This edition covers 746 archive files and 2,298,277 case records, of which 1,815,083 are off-airport Part 77 notices and 483,194 are on-airport notices. Data as of September 12, 2026.
Scope. Every chart on this page uses off-airport Part 77 notices only. The on-airport archive has a different schema with no determination or height columns, so mixing the two would quietly change what "a filing" means partway through a chart.
Privacy. Aggregate counts include every case. Any table that names a party includes organisations only — cases the pipeline identified as filed by a private individual are excluded from those tables entirely.
Turnaround. Measured as the days between the entered date and the completion date on determined cases, for structure types with at least 500 determinations. Reported as a median, with the mean in the downloadable table. Cases still in review are excluded, which means a category with a long tail of unresolved cases will look slightly faster here than it feels.
Known limits. 2026 is a partial year and is drawn in grey wherever it appears. Structure categories are derived from the FAA's free-text structure type field by a classifier, so category boundaries are ours, not the FAA's. Airport counts use the nearest-airport field recorded on the notice, which is not the same as "filings affecting that airport's airspace". And these arenotices: a filing is a proposal, not a built structure.
Corrections. If a figure here contradicts something you know from inside this industry, we want to hear it. Email support@idea-engine.studio and we will check the query and publish a correction.
Download the data
Every aggregate table behind this report, as CSV. Free for any use, including commercial and editorial, under CC BY 4.0 with credit to LOS Analyzer. No signup.
- Filings by yearCSV
- Filings by structure typeCSV
- Structure type by yearCSV
- FAA review turnaroundCSV
- Filings by stateCSV
- Filings by airportCSV
- Determination outcomesCSV
- Top representativesCSV
- Top sponsorsCSV
- Expiring determinationsCSV
- Height distributionCSV
How to cite this
LOS Analyzer, "The State of FAA Obstruction Filings" (2026 edition), analysis of FAA OE/AAA public archive data as of September 12, 2026. https://los-analyzer.idea-engine.studio/reports/faa-obstruction-filings-2026
Source: FAA Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) public archive (oeaaa.faa.gov), data as of September 12, 2026. Compiled by LOS Analyzer (Idea Engine LLC). This is not an official FAA record or an FAA determination; the FAA's portal is authoritative. LOS Analyzer is not affiliated with or endorsed by the FAA.
Compiled analysis © Idea Engine LLC, licensed CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/) — credit 'LOS Analyzer'. Underlying FAA data is public domain.
The same credit and licence are in the download folder's README.txt.
Why we built this
We parse this archive because we screen structures against it
LOS Analyzer checks a proposed structure against FAA Part 77 surfaces and the control tower's line of sight to the runway, terrain-aware, before you file. The same data work that produced this report is what the screening runs on. It is a preliminary screening, not an FAA determination and not a substitute for a licensed engineering review.